Roads · ongoing
Harper-Pleebo Feeder Road Rehabilitation
Rehabilitation of critical feeder road sections linking Harper and Pleebo markets.
Progress
42%
Budget
$450,000
Spent
$180,000
District
Harper
- Funding
- County Budget / Partner Grant
- Contractor
- Southeast Roads Ltd
- Consultant
- InfraConsult Africa
- Timeline
- 2025-02-01 → 2026-11-30
Milestones
-
Site clearance & mobilizationcompleted · 100%
-
Base course completionin_progress · 55%
-
Final surfacing & handoverpending · 0%
Updates
-
Quarterly progress note2026-07-27 12:14:16
Work advanced on feeder road base layers despite seasonal rains.